Lymm Traffic News

National Grid Information on Road Closures in Lymm

Lymm Gas Mains & Service Replacement Programme January 2010 – July 2010



  • Bridgewater Street – Whitbarrow Road Duration – 3 weeks
  • The Cross Duration – 10 weeks
  • The Cross - Pepper Street Duration – 4 weeks
  • Rectory Lane Duration – 3 weeks
  • New Road Duration – 6 weeks

View a Map of road closures.

Total estimated duration of works is 26 weeks.

Diversion routes via Danebank Road – Rectory Lane – Church Road – Brookfield Road – Eagle Brow.

Diversion signs will be in place throughout the duration of the works.


Customer Service Information

A Customer Liaison Officer will be available upon request throughout the duration of our works. To request a visit or any other enquiries regarding this project, please contact our customer service team on the number below.

00800 521 660 (Please select option 5 then option 2)


Shuttle Bus Service

Please note when the Road closure is in place for New Road (final 6 weeks of the project), the Lymm Cross bus stop will be out of use.

The bus numbers that will be affected are 5, 6 and 38.

There will be a shuttle bus service available to transport commuters to and from the Lymm Cross bus stop (adjacent to the Spar shop) to Lymm Church and Rush Green Road bus stops, where the normal bus service will resume.

More extensive information on road closures.